DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2016-WA]
Tacoma Public Utilities; Notice of Tacoma Public Utilities'
Request to Use Alternative Procedures in Filing a License Application
January 7, 1998.
By letter dated December 16, 1997, Tacoma Public Utilities (Tacoma)
asked to use an alternative procedure in filing an application for a
new major license for its Cowlitz River Project No. 2016.\1\ Tacoma has
demonstrated that they have made an effort to contact all resource
agencies, Indian tribes, nongovernmental organizations (NGOs), and
others affected by the applicant's proposal, and that a consensus
exists that the use of an alternative procedure is appropriate in this
case. Tacoma also submitted a communication protocol and a Memorandum
of Agreement that is supported by most interested entities.
---------------------------------------------------------------------------
\1\ The 462-megawatt project consists of the Mayfield Dam and
Powerhouse, Mossyrock Dam and Powerhouse, Cowlitz Salmon Hatchery,
Cowlitz Trout Hatchery, Mossyrock Park, Taidnapam Park, and other
associated facilities.
---------------------------------------------------------------------------
The purpose of this notice is to invite any additional comments on
Tacoma's request to use the alternative procedure, as required under
the final rule for Regulations for the Licensing of Hydroelectric
Projects.\2\ Additional notices seeking comments on the specific
project proposal, interventions and protests, and recommended terms and
conditions will be issued at a later date.
---------------------------------------------------------------------------
\2\ 81 FERC para. 61,103 (1997).
---------------------------------------------------------------------------
The alternative procedure being requested here combines the
prefiling consultation process with the environmental review process,
allowing the applicant to complete and file an Environmental Assessment
(EA) in lieu of Exhibit E of the license application. This differs from
the traditional process, in which the applicant consults with agencies,
Indian tribes, and NGOs during preparation of the application for the
license and before filing it, but the Commission staff performs the
environmental review after the application is filed. The alternative
procedure is intended to simplify and expedite the licensing process by
combining the prefiling consultation and environmental review processes
into a single process, to facilitate greater participation, and to
improve communication and cooperation among the participants. The
alternative procedure can be tailored to the particular project under
consideration.
Applicant-Prepared EA Process and the Cowlitz Project Schedule
On May 3, 1996, Tacoma distributed an Initial Stage Consultation
document for the Cowlitz Project to state and federal resource
agencies, Indian Tribes, and NGOs. Tacoma scheduled a consultation
meeting and site visit for all interested parties on June 26 and 28,
1996, respectively, to solicit study requests from participants. Tacoma
also held a public meeting in Mossyrock, Washington on June 27, 1996,
to solicit comments on the relicensing of the Cowlitz Project. Notices
announcing the meetings and site visit were published locally, as
required by Commission regulations.
Tacoma has been working collaboratively with the various interested
entities to refine the scope of studies identified during the initial
consultation meetings and during subsequent resource group meetings. On
April 10, 1996, Tacoma issued a report describing the results of
aquatic studies completed in 1996. On November 24, 1997, Tacoma
distributed a technical report summarizing the scope, method, and
results of all studies completed in 1997.
Public scoping meetings are planned for Spring 1998. Notice of the
scoping meetings and requests for additional studies will be published
at least 30 days prior to the meetings. The application, including any
applicant-prepared EA, must be filed with the Commission on or before
December 31, 1999, which is two years before the date of expiration of
the existing license.
Comments
Interested parties have 30 days from the date of this notice to
file with the Commission, any comments on Tacoma's proposal to use the
alternative procedures to file an application for the Cowlitz
Hydroelectric Project.
Filing Requirements
The comments must be filed by providing an original and 8 copies as
required by the Commission's regulations to: Federal Energy Regulatory
Commission, Office of the Secretary, Dockets--Room 1A, 888 First
Street, NE, Washington, DC 20426.
All comment filings must bear the heading ``Comments on the
Alternative Procedure,'' and include the project name and number
(Cowlitz Hydroelectric Project, No. 2016).
For further information, please contact David Turner of the Federal
Energy Regulatory Commission at (202) 219-2844 or e-mail at
david.turner@ferc.fed.us.
David P. Boergers,
Acting Secretary.
[FR Doc. 98-726 Filed 1-12-98; 8:45 am]
BILLING CODE 6717-01-M
Browse by Year
/ 1998
/ January
/ Tuesday, January 13, 1998
Bankruptcy - Debt Consolidation - Guitar Lessons - Credit Cards
|
|